This project was approved by City Council on February 18, 2026.
North Park Ventures & SNS Realty Group have proposed a zoning change from B3-2 to B2-5 to construct a 92-unit building with 51 2-bedroom apartments, 41 1-bedroom apartments, and 25 parking spaces. The proposed 5-story building would be constructed on the site of the now-vacant Torstenson’s Glass facility and will back up to the train. The development team would remove the current curb cut along this street, as part of this project. This project would include 15% (14) affordable housing units as part of the Affordable Requirements Ordinance.
Demolition Schedule:
- Demolition- End of July 2026 through Mid-August 2026
- Excavation and Foundation- Mid August 2026 through Mid October 2026
- Building- Mid-October 2026 through April 2028.
Supporting Documents:
- Updated 3233 N Sheffield Plans and Elevations – 2/6/26
- Revised rendering of 3233 N Sheffield Project – 10/20/25
- 3233 N Sheffield East Lake View Neighbors Presentation – 8/5/25
- 3233 N Sheffield Site Plan Announcement Proposal – 8/1/25