Water Main Projects
N Southport Ave Water Main (Addison to Irving Park)
- Construction Crew: Joel Kennedy Construction
- Water Main Dimensions: 8-inches in diameter, 4,375 ft. in length
- Completion Date (water main installation only): TBD (subject to change)
- Street Restoration (asphalt): TBD
*the street will be restored so that traffic and parking are not impacted - Street Closures: there will be periodic closures of N Southport while crews are working
- Parking Restriction: Parking will be restricted/limited throughout the duration of the project, Monday – Friday
- Water Shutoffs: residents & businesses will receive advanced notice of all scheduled shutoffs. In the event of an emergency shutoff, the construction crew will not be able to provide advanced notice
- *Please note: parking will be restricted during working hours throughout the duration of the project. When necessary, there will be periodic lane closures to ensure the safety of pedestrians and vehicles. When lane closures are necessary, construction crews will post detour signs to help navigate traffic.
W. Barry Ave Water Main (Clark to Kenmore)
- Contractor: Joel Kennedy Construction Corp.
- Water Main Dimensions: 8-inches in diameter, 1,320 ft. in length
- Completion Date (water main installation only): end of November (subject to change)
- Street Restoration (asphalt): Spring of 2014
*the street will be restored so that traffic and parking are not impacted at the end of November - Street Closures: there will be periodic closures of W. Barry while crews are working
- Parking Restriction: Parking will be restricted/limited throughout the duration of the project, Monday – Friday
- Water Shutoffs: residents will receive advanced notice of all scheduled shutoffs. In the event of an emergency shutoff, the construction crew will not be able to provide advanced notice.