Water Main Projects
N Broadway Water Main (Diversey to Wellington)
- Construction Crew: Reliable Construction
- Water Main Dimensions: 8-inches in diameter, 1,453 ft. in length
- Completion Date (water main installation only): TBD (subject to change)
- Street Restoration (asphalt): TBD
*the street will be restored so that traffic and parking are not impacted - Street Closures: there will be periodic closures of N Broadway while crews are working
- Parking Restriction: Parking will be restricted/limited throughout the duration of the project, Monday – Friday
- Water Shutoffs: residents & businesses will receive advanced notice of all scheduled shutoffs. In the event of an emergency shutoff, the construction crew will not be able to provide advanced notice
- * Please note: parking will be restricted during working hours throughout the duration of the project. When necessary, there will be periodic lane closures to ensure the safety of pedestrians and vehicles. When lane closures are necessary, construction crews will post detour signs to help navigate traffic.
N Lakewood Water Main (Belmont to Roscoe)
- Construction Crew: City of Chicago
- Water Main Dimensions: 8-inches in diameter, 1,280 ft. in length
- Completion Date (water main installation only): TBD (subject to change)
- Street Restoration (asphalt): TBD
*the street will be restored so that traffic and parking are not impacted - Street Closures: there will be periodic closures of N Lakewood while crews are working
- Parking Restriction: Parking will be restricted/limited throughout the duration of the project, Monday – Friday
- Water Shutoffs: residents & businesses will receive advanced notice of all scheduled shutoffs. In the event of an emergency shutoff, the construction crew will not be able to provide advanced notice
- * Please note: parking will be restricted during working hours throughout the duration of the project. When necessary, there will be periodic lane closures to ensure the safety of pedestrians and vehicles. When lane closures are necessary, construction crews will post detour signs to help navigate traffic.
W Melrose Water Main (Racine to Southport)
- Construction Crew: City of Chicago
- Water Main Dimensions: 8-inches in diameter, 1,284 ft. in length
- Completion Date (water main installation only): TBD (subject to change)
- Street Restoration (asphalt): TBD
*the street will be restored so that traffic and parking are not impacted - Street Closures: there will be periodic closures of W Melrose while crews are working
- Parking Restriction: Parking will be restricted/limited throughout the duration of the project, Monday – Friday
- Water Shutoffs: residents & businesses will receive advanced notice of all scheduled shutoffs. In the event of an emergency shutoff, the construction crew will not be able to provide advanced notice
- * Please note: parking will be restricted during working hours throughout the duration of the project. When necessary, there will be periodic lane closures to ensure the safety of pedestrians and vehicles. When lane closures are necessary, construction crews will post detour signs to help navigate traffic.
W Roscoe Water Main (Sheffield to Racine)
- Construction Crew: Reliable Construction
- Water Main Dimensions: 8-inches in diameter, 1,317 ft. in length
- Completion Date (water main installation only): TBD (subject to change)
- Street Restoration (asphalt): TBD
*the street will be restored so that traffic and parking are not impacted - Street Closures: there will be periodic closures of W Roscoe while crews are working
- Parking Restriction: Parking will be restricted/limited throughout the duration of the project, Monday – Friday
- Water Shutoffs: residents & businesses will receive advanced notice of all scheduled shutoffs. In the event of an emergency shutoff, the construction crew will not be able to provide advanced notice
- * Please note: parking will be restricted during working hours throughout the duration of the project. When necessary, there will be periodic lane closures to ensure the safety of pedestrians and vehicles. When lane closures are necessary, construction crews will post detour signs to help navigate traffic.
N Clifton Water Main (Waveland to Grace)
- Construction Crew:
- Water Main Dimensions: 8-inches in diameter
- Completion Date (water main installation only): TBD (subject to change)
- Street Restoration (asphalt): TBD
*the street will be restored so that traffic and parking are not impacted - Street Closures: there will be periodic closures of N Clifton while crews are working
- Parking Restriction: Parking will be restricted/limited throughout the duration of the project, Monday – Friday
- Water Shutoffs: residents & businesses will receive advanced notice of all scheduled shutoffs. In the event of an emergency shutoff, the construction crew will not be able to provide advanced notice
- * Please note: parking will be restricted during working hours throughout the duration of the project. When necessary, there will be periodic lane closures to ensure the safety of pedestrians and vehicles. When lane closures are necessary, construction crews will post detour signs to help navigate traffic.
N Greenview Water Main (Grace to Byron)
- Construction Crew: Reliable Construction
- Water Main Dimensions: 8-inches in diameter
- Completion Date (water main installation only): TBD (subject to change)
- Street Restoration (asphalt): TBD
*the street will be restored so that traffic and parking are not impacted - Street Closures: there will be periodic closures of N Greenview while crews are working
- Parking Restriction: Parking will be restricted/limited throughout the duration of the project, Monday – Friday
- Water Shutoffs: residents & businesses will receive advanced notice of all scheduled shutoffs. In the event of an emergency shutoff, the construction crew will not be able to provide advanced notice
- * Please note: parking will be restricted during working hours throughout the duration of the project. When necessary, there will be periodic lane closures to ensure the safety of pedestrians and vehicles. When lane closures are necessary, construction crews will post detour signs to help navigate traffic.
Sewer Main Projects
N Sheridan Sewer Main (Oakdale to Wellington)
- Construction Crew: City of chicago
- Sewer Main Dimensions:
- Completion Date (water main installation only): TBD (subject to change)
- Street Restoration (asphalt): TBD
*the street will be restored so that traffic and parking are not impacted - Street Closures: there will be periodic closures of N Lakewood while crews are working
- Parking Restriction: Parking will be restricted/limited throughout the duration of the project, Monday – Friday
- * Please note: parking will be restricted during working hours throughout the duration of the project. When necessary, there will be periodic lane closures to ensure the safety of pedestrians and vehicles. When lane closures are necessary, construction crews will post detour signs to help navigate traffic.
N Clark/N Halsted/WBarry/W Fletcher Sewer Main (Wellington to Belmont)
Water Management crews installed new sewers in N. Halsted Street (W. Wellington Ave. to W. Barry Ave.), in N. Clark Street (W. Barry Ave. to W. Fletcher Ave.), in W. Fletcher Ave. (N. Clark St. to 161’ West) and in W. Barry Ave.( N. Clark St. to 346’ West). The old pipe dates back to 1886, and needs to be replaced
- Construction Crew: City of Chicago
- Sewer Main Dimensions: varies
- Completion Date (water main installation only): TBD (subject to change)
- Street Restoration (asphalt): TBD
*the street will be restored so that traffic and parking are not impacted - Street Closures: there will be periodic closures of N Lakewood while crews are working
- Parking Restriction: Parking will be restricted/limited throughout the duration of the project, Monday – Friday
- * Please note: parking will be restricted during working hours throughout the duration of the project. When necessary, there will be periodic lane closures to ensure the safety of pedestrians and vehicles. When lane closures are necessary, construction crews will post detour signs to help navigate traffic.